Cisco announces the end-of-sale and end-of-life dates for CloudCenter 4.8.

The following table describes the end-of-life milestones, definitions, and dates for CloudCenter 4.8.

Milestone

Definition

CloudCenter 4.8

Major Release Date

The date CloudCenter 4.8 was released for the first time.

First Release Date for CloudCenter 4.8.0.

May 15, 2017
End-of-Life Announcement Date

The date the document that announces the end-of-sale and end-of-life of a product is distributed to the general public.

6 months ahead of the End-of-Support Date

May 14, 2018

Last Date to Download Software

The last-possible ship date that can be requested of Cisco and/or its contract manufacturers. Actual ship date is dependent on lead time.

6 months ahead of the End-of-Support Date

May 14, 2018

End-of-Software Maintenance Date

The last date that Cisco Engineering may release any final software maintenance releases or bug fixes. After this date, Cisco Engineering will no longer develop, repair, maintain, or test the product software.

18 months from the Major Release date

November 14, 2018


End-of-Life Date

The last date to receive applicable service and support for the product as entitled by active service contracts or by warranty terms and conditions. After this date, all support services for the product are unavailable, and the product becomes obsolete.

18 months from the Major Release date

November 14, 2018